Melbourne Museum

26%

Electrical Energy Saving
Savings

15%

Gas Savings

197

High-Priority
Ticket Closure Rate

366

Total Ticket
Closure Rate

11.9%

Demand Reduction
Savings

$163,890

Total Energy Savings

5 months

Investment Payback

$24,090

Demand Reduction

Melbourne Museum is the largest museum in the southern hemisphere, covering 70,000 m2. Year-on-year, Melbourne Museum consistently ranks as one of the top tourist destinations in Australia, garnering an annual footfall of almost one million visitors. Located in Carlton Gardens, the museum is a contemporary gallery home to natural and cultural history artifacts, the Sidney Myer Amphitheatre, The Age Theatre and the world’s largest IMAX Theatre screen.

In 2016, the museum invested heavily in a new building management system or BMS, to help meet the ever-evolving demands of managing a complex public asset, especially one that houses sensitive and significant cultural artifacts.

CIM Enviro was employed for BMS Commissioning Validation using fault detection and diagnosis (FDD) and data analytics. All too often, the assets and systems that building owners inherit are not to the standard that they paid for. Knowing this, the Melbourne Museum employed CIM Enviro to continuously monitor and validate the real-time commissioning of their new BMS. CIM Enviro provides benefits that a BMS cannot provide on its own. These include independent reporting on BMS and contractor performance, root-cause diagnosis of faults, cost-of-asset-failure calculation and data-driven strategies on how to sweat assets whilst remaining compliant.

Throughout the Defects Liability Period (DLP), CIM Enviro’s ACE Platform was able to deliver real-time data that assured Melbourne Museum would inherit a fully optimized and defect-free building.

Over the initial nine-month period, the ACE Platform identified 117 BMS and mechanical-asset faults across the estate, which may have otherwise gone unnoticed and been loaded onto the museum post DLP.

By resolving these 117 issues, Melbourne Museum was on track to reduce their annual energy bill by $203,000 – a 20% reduction on electricity and 28% on gas. Additionally, the museum achieved a $35,000 saving from resetting their demand threshold. All of this was achieved for a 4.5 month investment payback, a payback that comes three to four times faster than many other industry practices. Currently, CIM Enviro’s main objective within the Melbourne Museum is energy optimization, specifically in gas and electricity usage, as well as maintenance related FDD. One of the main challenges unique with cultural institutions such as museums is maintaining optimum moisture content.

The materials used to make and conserve artworks and artifacts are often organic (e.g. wood, bone, ivory, leather) and are therefore hygroscopic – they are sensitive to and affected by moisture content in the surrounding air. If the atmosphere is too damp, they will expand as they absorb moisture. Too dry and they will lose moisture and cause the structure of wooden artifacts to undergo detrimental chemical and physical changes.

Temperature and humidity are inextricably linked, making temperature-humidity control essential, especially as room temperature is often established according to the needs of visitors. Melbourne Musem’s onsite team was in search of a matrix to determine their HVAC equipment and control systems’ performance in maintaining the optimum humidity levels in the space, as well as use it to streamline their maintenance routine. Unfortunately, humidity control is often very energy consuming.

In response to these challenges, CIM Enviro has been working with the museum team to implement revised energy efficient control strategies that wouldn’t compromise space conditions.

CIM Enviro has designed a simple dashboard to provide easily digestible snapshots of each zone’s humidity KPI and highlights the problem areas that need immediate attention and action.

In the period between October 2017 and September 2018, CIM Enviro’s ACE Platform has also allowed Melbourne Museum to achieve $163,890 in energy savings. This is inclusive of a 26% electrical energy saving and 15% gas savings, both lower than the normalized model. The ACE Platform identified and resolved 366 fault tickets, 197 of which were high priority, providing a five-month investment payback and an 11.9% demand reduction, quantifying to $24,090 annually.

In partnering with CIM Enviro, Melbourne Museum has been able to ensure that through advanced machine learning and continuous data analytics, they have inherited a building worth its value that can safely protect some of Australia’s most treasured artifacts.

QUICK FACTS:

Location: Carlton Gardens, Victoria
Building Type: Cultural Institution
Building Size: 70, 000 m²
Owned By: Dexus
CIM Service Type: Managed Service

OBJECTIVES

  • BMS Commissioning Validation
  • Energy Optimisation
  • Gas usage reduction
  • Electricity usage reduction
  • Maintenance related FDD

OPPORTUNITIES:

  • Humidity control – maintaining optimum moisture content in the Museum Galleries
  • Streamlined maintenance routine – revised energy efficient control strategies

WANT TO CONNECT?

From energy optimisation through continuous fine tuning of existing HVAC systems, to total facility management with proactive maintenance planning and contract renegotiation, it all starts with enabling the ACE Platform on site.

Subscribe to our newsletter.

Australia

+61(0)2 8971 4066

Level 3, 55 Harrington Street,
The Rocks, NSW 2000

9am-5pm, Monday to Friday

Ireland

+353 (087) 737 3683
+353 (0)1 254 8549

20 Harcourt Street,
Dublin 2, D02 PF99

Follow

Website design by Sailor Studio